Each project will require en energy baseline to measure the save energy (pEUI). Refer to the "How to set a project" article if you're not familiar with steps that precede setting up a baseline.

Step-by-step guide

To set up a project baseline:

  1. After completing the "Extended Project Data Section" click on "Configure Use Type"
  2. In the "Configure Your Use Type" section select use type, enter project area then click on "Define Project Baseline"
  3. In the "Baseline Energy Use" section, enter the baseline EUI and source if you have them. If you don't have the baseline and source, the system will calculate the baseline based on the CBECS 2003 data and rationality. 
  4. Click "Save" or continue by clicking "set target energy use".
  5. At any point, you can click on the 'back:' button to go back to the previous section and make any changes.


Info

Filter by label (Content by label)
showLabelsfalse
max5
spacesDDXWIK
showSpacefalse
sortmodified
reversetrue
typepage
cqllabel = "kb-how-to-article" and type = "page" and space = "DDXWIK"
labelskb-how-to-article

...

Page Properties
hiddentrue


Related issues